Work zones and detours - Northwest Region

North Central Region work zones and detour map.

Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, Sawyer, St. Croix, Taylor, Trempealeau and Washburn counties.

Note - This info. is updated bi-weekly, is travel info. for projects lasting longer than two weeks, and only shows info. available at the time of its creation. It IS NOT real-time information.

Visit Wisconsin 511 Travel info. or Dial 511 for the most current road closures/travel information.

View larger NW region map


Notes:

Proposed end dates are estimates. A number of issues may delay the completion of a project. (Ex. Severe weather, forest/prairie fires, discovery of endangered species, unearthing archeological relics, contractors unable to fulfill their obligation, previously unknown environmental hazards, construction accidents, etc.).


The list below is sorted by county, then by highway.

 

 

 

 

 

Key: NB - northbound, EB - eastbound, SB – southbound, WB - westbound, DRWY – driveway, JCT – junction, RAB - roundabout
Map ID Region County Highway Description Proposed start date Proposed end date
5 NW ASHLAND US 2
US 2 EB
-FULL CLOSURE:  INDUSTRIAL PARK RD TO SUM RD, 4/27/15 TO 5/29/15
**DETOUR: FROM US 2 EB - SOUTH ON INDUSTRIAL PARK  RD TO TOLL RD - EAST ON TOLL RD TO SUM RD - NORTH ON SUM RD BACK TO US 2 EB
 
US 2 WB
-FULL CLOSURE:  SUM RD TO INDUSTRIAL PARK RD, 4/27/15 TO 5/29/15
**DETOUR: FROM US 2 WB - SOUTH ON SUM RD TO TOLL RD - WEST ON TOLL RD TO INDUSTRIAL PARK RD - NORTH ON INDUSTRIAL PARK RD BACK TO US 2 WB
Monday, April 27, 2015 Friday, May 29, 2015
51 NW BARRON WIS 48
WIS 48 EB
-FLAGGING OPERATION (14' LANE WIDTH RESTRICTION):  NORTH ST TO COUNTY NN, 4/13/15 TO 7/31/15, FROM 6:00 AM TO 8:00 PM
-LANE RESTRICTION (10' LANE WIDTH RESTRICTION):  RED CEDAR RIVER, 4/15/15 TO 5/8/15, FROM 12:00 AM TO 12:00 AM
-VARIOUS LANES CLOSED (14' LANE WIDTH RESTRICTION):  COUNTY SS TO NORTH ST, 4/13/15 TO 7/16/15, FROM 6:00 AM TO 8:00 PM
 
WIS 48 WB
-FLAGGING OPERATION (14' LANE WIDTH RESTRICTION):  COUNTY NN TO NORTH ST, 4/13/15 TO 7/31/15, FROM 6:00 AM TO 8:00 PM
-LANE RESTRICTION (10' LANE WIDTH RESTRICTION):  RED CEDAR RIVER, 4/15/15 TO 5/15/15, FROM 12:00 AM TO 12:00 AM
-VARIOUS LANES CLOSED (12' LANE WIDTH RESTRICTION):  NORTH ST TO WIS 48 EB (BEGIN DIVIDED), 4/13/15 TO 7/17/15, FROM 6:00 AM TO 8:00 PM
Monday, April 13, 2015 Friday, July 31, 2015
76 NW BAYFIELD US 2/WIS 13
US 2 EB
-FLAGGING OPERATION (15' LANE WIDTH RESTRICTION):  COUNTY G TO BAYFIELD - ASHLAND CO LINE, 4/27/15 TO 5/8/15
 
US 2 WB/WIS 13 NB
-FLAGGING OPERATION (15' LANE WIDTH RESTRICTION):  ASHLAND - BAYFIELD CO LINE TO E ONDOSSAGON RD, 4/27/15 TO 5/8/15
**DETOUR: TRAFFIC FROM THE WEST ON US 2 WILL BE DETOURED ON WIS 137 TO WIS 112 TO US 2. THEN WILL GO WEST ON US 2 TO THE ROUNDABOUT AND ENTER WIS 13 NB AS USUAL. THIS WILL BE IN EFFECT AT AROUND 11 AM ON THE 1 DAY OF CONSTRUCTION.
-FLAGGING OPERATION (15' LANE WIDTH RESTRICTION):  ASHLAND - BAYFIELD CO LINE TO N FISH CREEK, 4/27/15 TO 5/8/15
 
WIS 13 SB
-FLAGGING OPERATION (15' LANE WIDTH RESTRICTION):  E ONDOSSAGON RD TO BAYFIELD - ASHLAND CO LINE, 4/27/15 TO 5/8/15
**DETOUR: WIS 13 SB TRAFFIC WILL BE DETOURED ABOUT 10AM ON 1 DAY DURING THE WEEK OF APRIL 27TH. TRAFFIC WILL BE DETOURED WEST TO WIS 137, THEN EAST TO WIS 112, THEN NORTH BACK TO US 2. THIS WILL BE IN EFFECT UNTIL 7AM THE FOLLOWING DAY.
Monday, April 27, 2015 Friday, May 08, 2015
18 NW BAYFIELD WIS 13
WIS 13 NB
-FLAGGING OPERATION (15' LANE WIDTH RESTRICTION):  ECHO VALLEY RD TO OLD 13 RD, 3/16/15 TO 7/31/15
 
WIS 13 SB
-FLAGGING OPERATION (15' LANE WIDTH RESTRICTION):  OLD 13 RD TO ECHO VALLEY RD, 3/16/15 TO 7/31/15
Monday, March 16, 2015 Friday, July 31, 2015
36 NW DOUGLAS US 2
US 2 EB
-FULL CLOSURE:  MINNESOTA-WISCONSIN STATE LINE TO ELMIRA AVE, 4/13/15 TO 11/2/15
**DETOUR: NORTH ON I-35 TO I-535. SOUTH ON I-535 ACROSS BLATNIK BRIDGE TO US 53. SOUTH ON US 53 TO US 2 (BELKNAP STREET).
 
US 2 WB
-SINGLE LANE CLOSED (16' LANE WIDTH RESTRICTION):  GARFIEID AVE TO ST LOUIS RIVER, 3/30/15 TO 11/2/15
Monday, March 30, 2015 Monday, November 02, 2015
64 NW DOUGLAS US 2/US 53
US 2 EB/US 53 SB
-LEFT SHOULDER CLOSED (33' LANE WIDTH RESTRICTION):  ON RAMP FROM COUNTY Z TO ON RAMP FROM WEIGH STATION, 4/13/15 TO 11/30/15
 
US 2 WB/US 53 NB
-LEFT SHOULDER CLOSED (33' LANE WIDTH RESTRICTION):  OFF RAMP TO WEIGH STATION TO ON RAMP FROM WEIGH STATION, 4/13/15 TO 10/31/15
Monday, April 13, 2015 Monday, November 30, 2015
77 NW DOUGLAS WIS 27
WIS 27 NB
-FLAGGING OPERATION (16' LANE WIDTH RESTRICTION):  BAYFIELD - DOUGLAS CO LINE TO RUSH LAKE RD, 4/14/15 TO 4/23/15, FROM 7:00 AM TO 3:00 PM
Tuesday, April 14, 2015 Thursday, April 23, 2015
52 NW DUNN I-94
I-94 EB
-VARIOUS LANES CLOSED (16' LANE WIDTH RESTRICTION):  RED CEDAR RIVER TO MILE MARKER 51, 4/15/15 TO 5/22/15
 
I-94 WB
-VARIOUS LANES CLOSED (16' LANE WIDTH RESTRICTION):  MILE MARKER 51 TO RED CEDAR RIVER, 4/15/15 TO 5/22/15
Monday, April 13, 2015 Friday, May 22, 2015
53 NW JACKSON I-94
I-94 EB
-SINGLE LANE CLOSED (16' LANE WIDTH RESTRICTION):  MILE MARKER 120 TO OFF RAMP TO COUNTY O, 4/13/15 TO 5/21/15, FROM 6:00 PM TO 11:00 AM
Monday, April 13, 2015 Thursday, May 21, 2015
38 NW PIERCE WIS 72
WIS 72 EB
-SINGLE LANE CLOSED (14' LANE WIDTH RESTRICTION):  EAU GALLE RIVER TO EAU GALLE RIVER, 4/6/15 TO 5/4/15, FROM 7:00 AM TO 7:00 AM
 
WIS 72 WB
-SINGLE LANE CLOSED (14' LANE WIDTH RESTRICTION):  EAU GALLE RIVER TO EAU GALLE RIVER, 4/6/15 TO 5/4/15, FROM 7:00 AM TO 7:00 AM
Monday, April 06, 2015 Monday, May 04, 2015
37 NW ST. CROIX I-94
I-94 EB
-VARIOUS LANES CLOSED (16' LANE WIDTH RESTRICTION):  COUNTY T TO 233RD STREET, 4/1/15 TO 5/22/15
 
I-94 WB
-VARIOUS LANES CLOSED (16' LANE WIDTH RESTRICTION):  233RD STREET TO COUNTY T, 4/1/15 TO 5/22/15
Wednesday, April 01, 2015 Friday, May 22, 2015
78 NW ST. CROIX WIS 35/WIS 64
WIS 35 NB/WIS 64 EB
-SINGLE LANE CLOSED (13' LANE WIDTH RESTRICTION):  20TH ST TO 150TH AVENUE, 4/27/15 TO 5/8/15
 
WIS 35 SB/WIS 64 WB
-LANE RESTRICTION (13' LANE WIDTH RESTRICTION):  150TH AVENUE TO SETTLERS WAY, 5/8/15 TO 8/31/15
-SINGLE LANE CLOSED (13' LANE WIDTH RESTRICTION):  150TH AVENUE TO SETTLERS WAY, 4/27/15 TO 5/8/15
Monday, April 27, 2015 Monday, August 31, 2015
65 NW WASHBURN US 63
US 63 NB
-FLAGGING OPERATION (13' LANE WIDTH RESTRICTION):  WOODYARD RD TO COUNTY B, 4/20/15 TO 6/7/15
 
US 63 SB
-FLAGGING OPERATION (13' LANE WIDTH RESTRICTION):  COUNTY B TO WOODYARD RD, 4/20/15 TO 6/7/15
Monday, April 20, 2015 Sunday, June 07, 2015

Top Return to top

SSI - Contacts Questions about the content of this page:
Work zones facilitator, workzones.dtid@dot.wi.gov
Last modified: Apr. 15, 2015

[an error occurred while processing this directive]